The plans to complete the development of the Dagan neighborhood were approved.

The works include paving the street, tree planting, layering asphalt and more.

The work will begin after Passover.

Attached is a plan according to streets that includes a date and estimated working time for each of the stages.

Phase 1 - Ha'Aluma for about 5 weeks between the dates 4/13-5/18

Phase 2 - HaKatzir for about 5 weeks between the dates 5/21-6/22

Phase 3 - HaCharish/HaDagan for about 4 weeks between the dates 6/25-7/13

Phase 4 - Ha'Omer /HaKatzir about 10 weeks between the dates 7/16-9/21

Phase 5 - Hazoriim is about 12 weeks between the dates 9/24-11/19

Phase 6 - Siach Hasadeh for about a week on 11/20-11/30

We are taking into account the needs of the residents, but the work will require street closures and blocking parking spaces which we will announce ahead of time.

Thank you for your cooperation.

Wishing you a Chag Sameach

May be an image of ‎map and ‎text that says '‎השלמות פיתוח בששונת הדגן - ×שבועות תאריכים: 13/7 25/6- החריש שבועות תאריכים: -18/5 3/4 שבועות תאריכים: 19/11 תאריכים:11/11 24/9- כ- שבועות תאריכים: 22/6 21/5- האלומה הקציר הזורעים כ- 10 שבועות תאריכים: 21/9 16/7 העומר כשבוע אחד תאריכים: תאריכים:1113-11112 שיח השדה מקרא: השלמות פיתוח סדר שלב ביצוע: שלבא -רח' האלומה שלב לבה'-רח'הזורעים שלבו'-רח'שיחהשדה‎'‎‎